    Install calcium carbonate vertical roller mill

    Article source:admin Popularity:Dateline:2020-03-06 16:35

    When you buy a roller mill for grinding calcium carbonate online, it's not surprised that you will receive the parts of the equipment instead of the assembled vertical roller mill, so it is necessary for us to know how to install them.
     
    First, calcium carbonate vertical roller mill installation preparation phase, need to prepare the plant, power supply.The height and length and width of the plant should leave room for easy maintenance and loading and under material. The factory building should have a cement floor with a thickness of about 10 cm. It is not required to cover all the plants with a thickness of about 10 cm. Simply put the main body of the vertical roller mill and the fan position into 9 cm thick cement. Other parts can be around 6 cm. To be ready to use the installed tools, general general tools can be solved, such as more than two wrenches, wiring clamps, crowbars, etc.
     
    Second, calcium carbonate vertical roller mill installation stage, the main work of the installation phase is to place the vertical roller mill mainframe in a predetermined position, place a rubber pad underneath, and install expansion bolts on the concrete floor. After the host is installed, the host and the fan are connected. The fan and the tee are connected by bolts, and the main unit and the tee are connected by soft.  Pay attention to the seal of the pipe when connecting the pipes to prevent air leakage. After the vertical roller mill pipe connection is completed, the wiring is completed, and the lines of the three motors are connected, and the installation phase is completed.
     
    As a professional manufacturer of grinding mills, Shuguang Heavy Machinery sells a variety of different types of mill equipment, including ball mills, Raymond mills, vertical mills, etc.Welcome to contact us for more details.
     
    Factory Address: Longjiang West Road, Shangjie District, Zhengzhou City
    Contact number: +86-371-67666660 676667
    Mobile phone: 0086 13523465141
    After-sales Service Department: 0371-67666667

    Keywords:vertical roller mill

    The same article

    HOT

    link

    CNC Processing Hardwa Raymond mill EPS Machine

    中国免费特黄大片